Xcel Blamed For Cost Overruns At Monticello Nuclear Plant
MINNEAPOLIS (AP) - An investigation by Minnesota utility regulators blames Xcel Energy Inc. for major cost overruns during a project to upgrade its nuclear plant in Monticello.
Xcel disagrees that it's to blame.
The experts hired by Minnesota utility regulators found Xcel managers didn't fully plan for the job and didn't have adequate oversight. The investigation also found Xcel misleadingly blamed the U.S. Nuclear Regulatory Commission for some costly delays.
The project rose from an estimated $320 million in 2008 to $665 million when it was completed last year. The final cost could reach $748 million.
The utility is asking regulators to have ratepayers pay for the cost of the upgrade.
Xcel will file a reply to issues raised in the investigation next month.
More From AM 1240 WJON
![Stearns History Museum’s John Decker; My Life [AUDIO]](http://townsquare.media/site/67/files/2024/07/attachment-John-Decker-young.jpg?w=980&q=75)
![Big Brothers Big Sisters Kicking Off Recruitment Campaign](http://townsquare.media/site/67/files/2024/07/attachment-2h-media-xGn1-bDVu8U-unsplash.jpg?w=980&q=75)
![St Cloud Drivers – Its a Roundabout – Not a 4-Way Stop](http://townsquare.media/site/66/files/2021/07/attachment-Roundabout.jpg?w=980&q=75)
![If You Like Odd Pizza Ingredients, This Might Be the Best in Minnesota](http://townsquare.media/site/66/files/2024/07/attachment-Zorbaz-Pizza-1.png?w=980&q=75)
![St. Cloud Man Sentenced for 2022 Murder](http://townsquare.media/site/67/files/2024/03/attachment-Paul-Coleman.jpg?w=980&q=75)
![Huge Muffin Recall From This Minnesota Favorite Bargain Store](http://townsquare.media/site/65/files/2024/07/attachment-joshua-flores-via-unsplash.jpg?w=980&q=75)
![I-94 Project Between Monticello and Albertville Starts Soon](http://townsquare.media/site/67/files/2018/04/Road-Construction.jpg?w=980&q=75)
![Buckvold Looking to Lead St. Cloud As Next Mayor](http://townsquare.media/site/67/files/2024/04/attachment-thumbnail_20240206-AnneBuckvold-LakeGeorgeStCloud-1.jpg?w=980&q=75)
![Support And Unity: Sherburne County Leaders Condemn Violence In Political Disagreements](http://townsquare.media/site/67/files/2024/07/attachment-Trump-AssassinationAttempt-GettyImages.jpg?w=980&q=75)